Contract N1081

NORTH SOUTH CORRIDOR (NSC)- CONTRACT N1081- Provision of Qualified Person Supervision for the Civil Contract N108.

The proposed 21.5km long North South Corridor (NSC) runs along the existing road corridor between ECP and Admiralty Road West. It will have grade-separated carriageways on the viaduct and tunnel dual 3-lanes; expect for the stretch of CTE and PIE where it will be dual 4 lanes. The NSC which is schedule to complete in end year 2026 will also feature bus priority and active mobility measures.

The tunnel section of the NSC is 12.3km long. For operation of the tunnel, 5 (five) facility buildings will be provided at Ang Mo Kio Town Garden West, Mary mount Road, PIE (Thomson Flyover), Kampong Java Road and Nicoll Highway. 2

Contract N108 is for Design and Construction of North-South Corridor (Tunnel) between Marymount Lane and Pemimpin Place.

Total Contract Duration-95 months

Project Commencement Date: March 2019

Estimated Project Completion Date: Dec 2026